A change of applicant, company name, address or representative can happen while a PCT application is still in its international phase. Rule 92bis provides a way for the International Bureau of WIPO to record certain changes in the request or demand. When China national phase entry is approaching, the useful question is which recorded details and supporting documents should reach the China filing team.

Begin by identifying what changed, when it changed and which application is affected. Use the ePCT handover checklist to coordinate access and the person authorized to handle the file. This guide focuses on changes to the PCT record and the handover to mainland China. Case-specific title, authority and document questions need individual review.

What belongs in the change file

Situation International record issue China handover item
Same legal entity with a changed name or address Specify the old and new particulars accurately Evidence explaining continuity and consistent Chinese and original-language names
Different applicant after an assignment Identify the old and new applicant and the affected application Assignment chain and the International Bureau’s notification
Change of agent or representative Check who may request the change and sign Authority documents and current contact details
China entry already filed Compare the PCT request with the Chinese file Ask the China agent what local steps remain
Request close to the limit Confirm International Bureau receipt before expiry Submission evidence and the separate national phase schedule

Handle the record and the China handover together

1. Classify the change before drafting the request

Rule 92bis covers certain particulars of the applicant, agent, common representative and inventor. A new business name can describe the same legal entity, while a transfer to another entity changes the person of the applicant. Build a before-and-after entry with the full names, addresses and application number. Keep the reason and supporting business document with that entry. If the underlying change is a transfer, use the China patent assignment handover checklist to assemble the sequence of parties and documents for China review. Ask the file’s representative to confirm how the change should be described if the business records are ambiguous. The public title of a corporate transaction rarely tells the whole story about which entity now holds the particular application.

2. Calendar the International Bureau’s receipt limit

Under Rule 92bis.1(b), the International Bureau will not record a request it receives after 30 months from the priority date. Calendar the date on which the Bureau must receive the request and leave time to resolve signatures, missing particulars or submission problems. WIPO recommends sending requests directly to the Bureau, preferably through ePCT. Delivery to another office close to the limit can leave insufficient time for the Bureau to receive it. China’s ordinary national phase entry period is also 30 months from the priority date. Its separate late-entry possibility up to 32 months, with a surcharge and the applicable requirements, does not extend the Rule 92bis receipt period. Ask the China agent to confirm the entry schedule for the actual case.

3. Submit through an authorized person and save the record

WIPO’s application-management page provides a route to the Rule 92bis request in ePCT. The request should identify the application and precisely state the change. Confirm which applicant or representative is making it and the supporting signatures and authority needed for that situation. A request from a new applicant without the written consent of the applicant of record needs documentary support. A new agent acting for that new applicant also needs to address the applicable power-of-attorney requirement. Coordinate this before submission. Save the request and its delivery evidence. If several pending applications are involved, check each number and deadline individually even where a combined request is used. A list that includes an unrelated file can spread a mistake across a portfolio.

4. Read the notification and reconcile the Chinese brief

When the International Bureau records a change, it issues Form PCT/IB/306. Read the old and new details, application number and any territorial scope shown. Reconcile the original name, Chinese rendering and address with the China instruction. CNIPA’s national-entry FAQ says a change already recorded and notified by the Bureau is used at entry without filing the same bibliographic change again or paying that change fee. Rule 121(1)(vi) requires evidence of the new applicant’s entitlement where necessary. Keep the assignment chain ready for the China agent to assess, including any special requirements for a transfer from mainland China to a foreign party. If China entry has already begun, have the agent reconcile the local record and remaining steps promptly.

5. Close both the request and the entry task

A complete handover should show the prior applicant, current applicant, reason for the change, request receipt, notification, supporting evidence and the China agent’s next action. Keep an outstanding-item line if recording is pending. Continue the separate entry preparations, including translations, authority and national forms. Review the China PCT entry guide with the current record so the entry instruction matches the party the team intends to name. If the 30-month recording period has passed, obtain advice on the national procedures available for the particular change. Keep proof of what was submitted and what remains to be done in each relevant office. Closing the corporate task internally is a separate milestone from receiving and reviewing the procedural records.

Example with a transfer before entry

Suppose a company transfers a pending PCT application to another company while China entry is being planned. The team first confirms the application number and the parties on the transfer instrument. It sends the authorized Rule 92bis request with enough time for International Bureau receipt before the 30-month point. It then checks the PCT/IB/306 notification against its own before-and-after record. This is a hypothetical planning example and does not describe an actual filing or outcome.

The China handover includes the transfer evidence, notification and consistent applicant details. If a second transfer took place, the team includes that link in the chain. If China entry was filed before the Bureau recorded the change, the agent compares the Chinese record and determines the follow-up. The team keeps the PCT recording task and the China entry task open until the responsible person confirms what has been completed for each.

Frequently asked questions

Can I use Rule 92bis to amend the technical disclosure?

The rule concerns specified particulars in the request or demand. Changes to claims, description or drawings have their own procedures. Tell the representative which kind of correction or amendment you actually need.

Will an IB notification remove the need for assignment evidence in China?

Keep the evidence ready for review. Current Chinese Rule 121(1)(vi) and CNIPA’s FAQ call for proof of entitlement where necessary. The agent should assess the actual change and the chain. CNIPA also explains that an IB-recorded change is used at entry without duplicating the same bibliographic-change filing.

What if the request is still pending when China entry approaches?

Tell the China agent what was requested and provide receipt evidence and the latest available record. Coordinate the applicant details and remaining documents while keeping the entry deadline under review.

Can an overseas applicant handle all China procedures directly?

WIPO’s China national chapter requires an agent if the applicant has no habitual residence or business office in the Chinese mainland. The agent must be a patent agency legally incorporated in China. Confirm authority and the local documents with that agency.

If the filing team needs help coordinating the change file, contact our team with the PCT number, current deadline and a brief description of what changed. Confirm any secure document-sharing arrangement before sending confidential transfer papers.

Official sources and application

Sources checked on 19 November 2026. This guide uses the current WIPO China chapter, applicable from 1 October 2026, and the international-phase guidance dated 23 April 2026. The time limit for International Bureau receipt runs from the priority date. China’s late-entry procedure is conditional and must be assessed for the actual file.

PCT Rule 92bis

WIPO PCT Applicant’s Guide, international phase

WIPO management routes and ePCT request

WIPO China national chapter

PCT Administrative Instructions, Section 422